Oko West, Guyana, October 7, 2025

News Summary

G Mining Ventures has lined up an initial US$387.5 million financing package for the Oko West gold project in Guyana, with an option to increase funding by US$150 million after closing, potentially totaling US$537.5 million. The package includes a US$350 million revolving credit facility and up to US$37.5 million in equipment finance from Komatsu. The company received a five-year environmental permit authorizing construction and operation, and management expects a Final Investment Decision imminently. The debt-based, non-dilutive financing, combined with existing cash flow, positions the project to advance toward construction and production.

G Mining secures financing package for Oko West that could reach US$537.5 million; environmental permit granted and final investment decision expected imminently

G Mining Ventures Corp. (TSX: GMIN; OTCQX: GMINF) has lined up a financing package that initially provides US$387.5 million for the Oko West gold project in Guyana, with an accordion option allowing lenders to increase the facility by a further US$150 million six months after closing. The company also received a five-year environmental permit authorizing construction and operation of Oko West, positioning management to take a final investment decision (FID) imminently.

Top-line finance and permit details

The initial financing package is comprised of a US$350 million revolving credit facility and up to US$37.5 million in equipment financing arranged with Komatsu Finance. If activated by lenders, the accordion increases total available financing to US$537.5 million. The environmental permit from Guyana’s Environmental Protection Agency is valid for five years and authorizes construction and operation through July 2030.

Financing structure and terms

Permitting, early works and project readiness

The environmental permit follows submission of a full Environmental and Social Impact Assessment and nearly two years of baseline studies. The permit allows construction activities and operation at Oko West and follows earlier authorizations that enabled limited early works. Early works began in March 2025 and have included development of a wharf, access roads and the permanent camp. Early works items for 2025 were planned at roughly US$200–240 million.

Next steps: FID and capital plan

With the EPA permit and financing arrangements in place, the company is positioned to make a formal FID on Oko West later in October 2025. The forthcoming decision is expected to set out the forecasted initial capital cost, amounts already invested and remaining expenditures to completion. The company has stated that approximately US$190 million has already been committed or negotiated for long-lead items such as mobile and marine equipment, grinding mills, a primary crusher and a power plant, and that initial equipment deliveries were expected in the second half of 2025.

Project economics, timeline and workforce

Financial position and company context

The company is using operating cash flow from a producing mine in Brazil to help fund development. Management characterizes the new financing as increasing financial capacity and flexibility while preserving equity ownership. The package is intended to support continued early works, procurement, and a prompt transition to full construction if the FID proceeds as planned.

Market and corporate notes

The company appointed a new vice-president of corporate development with experience across mining capital markets. Reported market movements showed the company’s shares rising in response to the financing and project progress earlier in October 2025. All forward-looking statements remain subject to customary risks, uncertainties and regulatory conditions.

Risks and caveats

The financing accordion is subject to lender approval and customary conditions and would only be available beginning six months after closing. Project timing, cost estimates, environmental approvals beyond the current permit, equipment deliveries and operational performance remain subject to risk. Statements about jobs, timing and returns are forward-looking and dependent on many factors that could cause actual results to differ.

Contact and follow-up

Further details on financing drawdowns, the full FID package, and the construction schedule are expected to be released by the company at the time of a formal construction decision.


FAQ

What is the total amount of financing available to Oko West?

The initial package provides US$387.5 million (a US$350 million revolving facility plus up to US$37.5 million in equipment financing) with an option for lenders to extend an additional US$150 million, bringing potential total financing to US$537.5 million.

Who are the main lenders and arrangers?

The facility is led by joint bookrunners and co-lead arrangers and includes multiple participating banks. Equipment finance is provided by Komatsu Finance through an agreement to fund mining and construction equipment.

Is the financing dilutive to shareholders?

The company describes the financing as non-dilutive, since it does not involve issuance of new equity as part of the package.

Has the project received environmental approval?

Yes. A five-year environmental permit authorizing construction and operation was issued and is valid through July 2030.

When will the company decide to start full construction?

Management has indicated a final investment decision is expected imminently, with a formal construction decision to be announced around the time of the FID later in October 2025.

What are the expected timelines for construction and production?

Construction is forecast to take about 34 months, and commercial production is targeted in the first half of 2028, subject to risks and approvals.

{
“@context”: “https://schema.org”,
“@type”: “FAQPage”,
“mainEntity”: [
{
“@type”: “Question”,
“name”: “What is the total amount of financing available to Oko West?”,
“acceptedAnswer”: {
“@type”: “Answer”,
“text”: “The initial package provides US$387.5 million (a US$350 million revolving facility plus up to US$37.5 million in equipment financing) with an option for lenders to extend an additional US$150 million, bringing potential total financing to US$537.5 million.”
}
},
{
“@type”: “Question”,
“name”: “Who are the main lenders and arrangers?”,
“acceptedAnswer”: {
“@type”: “Answer”,
“text”: “The facility is led by joint bookrunners and co-lead arrangers and includes multiple participating banks. Equipment finance is provided by Komatsu Finance through an agreement to fund mining and construction equipment.”
}
},
{
“@type”: “Question”,
“name”: “Is the financing dilutive to shareholders?”,
“acceptedAnswer”: {
“@type”: “Answer”,
“text”: “The company describes the financing as non-dilutive, since it does not involve issuance of new equity as part of the package.”
}
},
{
“@type”: “Question”,
“name”: “Has the project received environmental approval?”,
“acceptedAnswer”: {
“@type”: “Answer”,
“text”: “Yes. A five-year environmental permit authorizing construction and operation was issued and is valid through July 2030.”
}
},
{
“@type”: “Question”,
“name”: “When will the company decide to start full construction?”,
“acceptedAnswer”: {
“@type”: “Answer”,
“text”: “Management has indicated a final investment decision is expected imminently, with a formal construction decision to be announced around the time of the FID later in October 2025.”
}
},
{
“@type”: “Question”,
“name”: “What are the expected timelines for construction and production?”,
“acceptedAnswer”: {
“@type”: “Answer”,
“text”: “Construction is forecast to take about 34 months, and commercial production is targeted in the first half of 2028, subject to risks and approvals.”
}
}
]
}

Key features at a glance

Feature Detail
Initial financing US$387.5 million (US$350m revolver + up to US$37.5m equipment loan)
Accordion option Up to US$150 million available six months after closing, subject to lender approval
Interest SOFR + 0.1% credit spread adjustment + margin 2.75%–3.75% (net leverage dependent)
Equipment finance Komatsu Finance notes up to US$37.5 million
Environmental permit Five-year permit valid through July 2030 authorizing construction and operation
Location Oko West, Guyana, about 120 km southwest of Georgetown
Indicated resources ~80.3 Mt at 2.1 g/t Au (~5.4 Moz)
Construction timeline ~34 months to build; production expected H1 2028
Expected permanent jobs ~1,270 direct positions on average over the project life
Remaining capex ~US$909 million (company presentation)
Company funding sources Financing package plus cash flow from an existing producing mine

Deeper Dive: News & Info About This Topic

Additional Resources