Dongfeng completes 47,000 m² gigacasting plant 25 days early

China, September 8, 2025

News Summary

Dongfeng has finished construction of a 47,000 m² gigacasting factory 25 days ahead of schedule, allowing earlier equipment installation and commissioning. The single‑phase building will house ultra‑large die‑casting lines including a 16,000‑tonne unit and a 10,000‑tonne unit, positioning the company at the forefront of large‑format casting. Using Building Information Modeling (BIM) sped coordination and delivery. The project targets phased production capacity with an initial annual output goal of 200,000 components and a later scale‑up to 600,000 after additional lines are added. Investment is about 1 billion yuan and lines will be brought online gradually.

Dongfeng completes 47,000 m² gigacasting plant 25 days early; mass production set for June 2026

What happened: A new die‑casting plant built for a major Chinese automaker was completed 25 days ahead of schedule, finishing the factory shell that will host two ultra‑large gigacasting lines. The physical building covers 47,000 square meters and will be the central production base for the company’s gigacasting rollout.

Key facts up front

  • Construction started in November 2024 and the building was finished in a single phase, handed over nearly a month early.
  • The plant will house dual integrated die‑casting lines featuring 16,000‑tonne and 10,000‑tonne machines described as the largest of their kind globally.
  • Mass production is planned to start in June 2026.
  • Project investment is around 1 billion yuan, with a two‑phase plan to reach a total of 600,000 components per year once fully built out.

Construction and handover

The construction contractor reported early completion of the factory building. Project teams used Building Information Modeling (BIM) to speed design coordination and construction, which helped achieve handover ahead of contractual deadlines. The completed building is intended to serve as the core production base for the automaker’s gigacasting industrialization program.

Production lines and capacity

In the first phase, the site will be equipped with one 16,000‑tonne gigacasting line and one 10,000‑tonne line. That initial setup will give the plant an annual output capacity of 200,000 components. A second phase will add four more lines, bringing total annual output to 600,000 components. Components targeted include super‑large structural parts for new energy vehicles such as rear floor assemblies and battery casings.

Why the machines matter

Gigacasting uses ultra‑large die‑casting machines to form multiple parts into a single structural component under very high pressure. The approach aims to reduce part count, welding work, and assembly steps while strengthening body structures and improving safety and efficiency, especially for electric vehicles with large, heavy battery packs. The 16,000‑tonne capacity is highlighted as the largest currently available and marks a first for the automaker to adopt this size of machine.

Timeline and rollout

Although the factory building is already complete, the casting lines will be installed and commissioned in stages rather than all at once. The first phase installation of the two giant machines precedes planned mass production in June 2026. This staggered approach allows testing and ramping of output while later lines are added in the second phase.

Industry context

Gigacasting has moved quickly from a niche experiment to a mainstream assembly option in electric vehicle production. The method can cut weight, reduce the number of parts and welds, and lower some manufacturing costs by replacing many welding and stamping steps with a single large casting operation. That said, the approach brings tradeoffs: high initial equipment and tooling costs, possible metal distortion risks, and more complex repair processes if a large single part is damaged.

Technical and business implications

Advances in design, alloy formulation, cooling and heat treatment, and rapid mold testing have helped make very large castings practical at scale. Project documents state the plant will focus on research, production, and sales of super‑large gigacasting structural components for new energy vehicles. Expected benefits include higher output and improved line efficiency for NEV manufacturing, while the industry continues to balance cost, repairability, and quality concerns.

Photo credit

Photo credit for the project announcement is attributed to the construction contractor’s official account.


Frequently asked questions

What is gigacasting?

Gigacasting is a manufacturing method that uses very large die‑casting machines to create big, single structural parts for vehicles by injecting molten metal into a mold under high pressure. It reduces the number of parts and welding steps needed to build a vehicle body.

Why is a 16,000‑tonne machine notable?

A 16,000‑tonne machine provides extremely high clamping force, allowing the casting of larger, single pieces than smaller machines. That size enables production of very big components such as underbody assemblies and battery casings in fewer parts.

When will the plant start mass production?

Mass production is scheduled to begin in June 2026, following staged installation and commissioning of the casting lines.

How much will the project produce?

Phase one with two lines will be able to produce about 200,000 components per year. After adding four more lines in phase two, annual output is expected to reach 600,000 components.

What are the main tradeoffs of gigacasting?

Main tradeoffs include high upfront investment, potential challenges in repairing large single pieces after a crash, and technical risks such as metal distortion. These are balanced against reduced assembly steps, lower part counts and potential cost savings in high‑volume production.

Key features at a glance

Feature Detail
Factory area 47,000 m²
Start of construction November 2024
Handover 25 days ahead of schedule
Installed machines (phase 1) One 16,000‑tonne line and one 10,000‑tonne line
Planned mass production June 2026
Initial annual capacity 200,000 components (phase 1)
Full annual capacity 600,000 components (after phase 2)
Project investment About 1 billion yuan
Key technologies used Gigacasting machines, BIM for construction

Deeper Dive: News & Info About This Topic

Additional Resources

Author: Construction TX News

TEXAS STAFF WRITER The TEXAS STAFF WRITER represents the experienced team at constructiontxnews.com, your go-to source for actionable local news and information in Texas and beyond. Specializing in "news you can use," we cover essential topics like product reviews for personal and business needs, local business directories, politics, real estate trends, neighborhood insights, and state news affecting the area—with deep expertise drawn from years of dedicated reporting and strong community input, including local press releases and business updates. We deliver top reporting on high-value events such as the Texas Construction Expo, major infrastructure unveilings, and advancements in construction technology showcases. Our coverage extends to key organizations like the Associated General Contractors of Texas and the Texas Building Branch, plus leading businesses in construction and real estate that power the local economy such as Austin Commercial and CMiC Global. As part of the broader network, including constructioncanews.com, constructionnynews.com, and constructionflnews.com, we provide comprehensive, credible insights into the dynamic construction landscape across multiple states.

Construction TX News

TEXAS STAFF WRITER The TEXAS STAFF WRITER represents the experienced team at constructiontxnews.com, your go-to source for actionable local news and information in Texas and beyond. Specializing in "news you can use," we cover essential topics like product reviews for personal and business needs, local business directories, politics, real estate trends, neighborhood insights, and state news affecting the area—with deep expertise drawn from years of dedicated reporting and strong community input, including local press releases and business updates. We deliver top reporting on high-value events such as the Texas Construction Expo, major infrastructure unveilings, and advancements in construction technology showcases. Our coverage extends to key organizations like the Associated General Contractors of Texas and the Texas Building Branch, plus leading businesses in construction and real estate that power the local economy such as Austin Commercial and CMiC Global. As part of the broader network, including constructioncanews.com, constructionnynews.com, and constructionflnews.com, we provide comprehensive, credible insights into the dynamic construction landscape across multiple states.

Share
Published by
Construction TX News

Recent Posts

Princeton council to consider $6.3M loan for Mini‑System 36 sewer rehabilitation

, September 8, 2025 News Summary Princeton’s council will consider borrowing $6.3 million from the New…

7 hours ago

The Averly Richmond Hill breaks ground on $60M mixed-use project

Richmond Hill, Georgia, September 8, 2025 News Summary ECI Group has broken ground on The Averly…

7 hours ago

Czech industrial output accelerates as manufacturing and construction lift economy

Czech Republic, September 8, 2025 News Summary Industrial production in the Czech Republic strengthened, driven by…

7 hours ago

Pasadena Council to vote on Ramona Senior Housing lease and $5M state funding

Pasadena, California, September 8, 2025 News Summary The Pasadena City Council will consider an amended development…

8 hours ago

Latin America construction market faces strong demand amid diverging forecasts

Latin America, September 8, 2025 News Summary Two recent studies present conflicting size and growth estimates…

9 hours ago

Construction market set for steady rise as data‑centres and insurance deals reshape priorities

Dublin, Ireland, September 8, 2025 News Summary A major market study forecasts significant expansion in the…

9 hours ago